Construction update: September 2019

We are happy to announce that construction is continuing to progress well. Builders have confirmed completion is still on target for January 2020.

Read
The Atrium Lutwyche - Construction update - May 2019 - podium slab pour

Construction update: May 2019

As we say farewell to Autumn, we're very happy to announce that the podium slab pour is complete, marking the beginning of aboveground works!…

Read
The Atrium Lutwyche - Construction update - April 2019 - view of construction site

Construction update: April 2019

Despite the site closing down over Easter and ANZAC Day, April has still been a very productive month at The Atrium Lutwyche.

Read
The Atrium Lutwyche - Construction update - March 2019 banner

Construction update: March 2019

With the first quarter of 2019 now in our rear-view mirror, we're starting to see some big changes on site at The Atrium Lutwyche.

Read
Celebratory morning tea

Celebratory morning tea

Thank you to everyone that joined us on Friday 1 March to celebrate construction commencing at The Atrium Lutwyche and mark this exciting milestone.

Read
The Atrium Lutwyche - Construction update - February 2019 banner

Construction update: February 2019

February was a busy month on site at The Atrium Lutwyche. The team at McNab continued to excavate the underground car park and basement area.

Read
The Atrium Lutwyche - Construction update - January 2019

Construction update: January 2019

After a three and a half week break, the team at McNab are back on site and construction has recommenced at The Atrium Lutwyche.

Read
Construction update: December 2018

Construction update: December 2018

Foundation works are progressing well on site at The Atrium Lutwyche.16 concrete piles have now installed with works continuing in the New Year.

Read