As we say farewell to Autumn, we’re very happy to announce that there have been some major progress on site at The Atrium Lutwyche.

The upper slab pour B was completed at the beginning of May, followed by the entrance ramp into the basement.

The Atrium Lutwyche - Construction update - May 2019 - basement ramps

The team at McNab then began preparation for the podium/level 1 slab pour. Unlike the other levels, the podium slab is done in a single concrete pour and therefore required additional formwork and planning.

On 23 May, the podium slab pour was completed, marking the beginning of above ground works!

The Atrium Lutwyche - Construction update - May 2019 - podium slab pour

Over the next few weeks, scaffolding and formwork will go up on site in preparation for the level 2 slab pours.

Subscribe to event alerts

If you'd like to be notified by email whenever RSVPs are open for The Atrium Lutwyche's events, please enter your details below.